Economy · Brief
Riverport West gets $40 million federal grant
The city expects to break ground in about a year. The goal is to open the dock in 2029.

The Riverport West dock project received a $40 million federal grant from the U.S. Department of Transportation’s Maritime Administration, the city announced at the Oct. 27 City Commission meeting, according to its meeting summary.
The Port Infrastructure Development Program grant brings combined federal and state funding for the project to $78 million, the city said after Riverport Authority Executive Director James Garrett briefed commissioners.
That total includes state funding and a $24 million federal BUILD grant announced over the summer, the city said. That leaves about $14 million in state funding, based on the city’s figures.
The $78 million total is in line with the project’s estimated cost, the city said. On July 1, WKMS reported the project was expected to cost about $70 million, according to the Waterways Journal.
The project includes a dock with direct rail access next to the Triple Rail Site, less than two miles from the U.S. Department of Energy Paducah site, the city said. The new Ohio River port would be about nine miles from the existing riverport, WKMS reported.
What’s next
Next steps include finalizing grant agreements, developing a wetland mitigation plan and completing construction permits, the city said.
The city expects to break ground in about a year, followed by an estimated 18 months of construction, with a goal of opening the dock in 2029.
Sources and updates
Based on the City of Paducah’s Oct. 27, 2026, meeting summary and WKMS reporting from July 1, 2026. Checked Nov. 13, 2026.
Prepared with AI assistance from the City of Paducah’s meeting summary and WKMS reporting. How we use AI · Report a correction