I-24 bridge inspections will close one lane starting Dec. 7
Eastbound work is scheduled first, followed by westbound inspections the next week. One lane will stay open in the affected direction.
Drivers crossing the Ohio River on Interstate 24 should allow extra time during two weeks of inspections beginning Dec. 7, the Illinois Department of Transportation announced.
When lanes will close
Eastbound inspections are scheduled for Dec. 7–9 and westbound inspections for Dec. 14–16. When crews are working, one lane will close from 7 a.m. to 5 p.m. One lane will remain open in that direction.
Weather may change the schedule. IDOT says closures could occur on any day during the inspection period and warns drivers to expect long delays.
Separate from rehabilitation work
The agency describes the December work as routine inspections. Its Nov. 16 rehabilitation update had projected all lanes reopening Nov. 18 and staying open through winter until the next construction phase begins March 1, 2027. The newer notice adds temporary inspection closures to that winter outlook.
Check IDOT’s traveler information map before leaving. These are scheduled closures, not a report of current lane conditions.
Sources and updates
Sources checked Nov. 27, 2026: IDOT notices dated Nov. 25 and Nov. 16. Inspection dates are weather dependent.
Prepared with AI assistance and checked against the linked sources. The thumbnail is a ProPaducah graphic. How we use AI · Report a correction